How to Quote Decking Jobs
A practical quoting guide for Australian deck builders. Covers timber and composite material pricing, subframe costs, balustrade options, labour rates by material type, common job benchmarks, council permit triggers, licensing by state, and how to present quotes that win work and protect your margin.
Why accurate quoting decides whether a decking business grows or stalls
Decking sits at the intersection of carpentry skill and material cost management. The boards are the headline number the customer sees, but the subframe, fasteners, balustrades, stairs, finishing, and council fees underneath often add up to more than the boards themselves. Deck builders who win consistently quote all of those layers honestly. The ones who struggle tend to ballpark the subframe, forget the finishing, and absorb the council drawing costs to keep the topline number low.
The gap between a profitable deck build and one that breaks even is usually found in three places: underpricing the subframe, failing to account for site conditions (slopes, access, demolition of the old deck), and not charging for the finishing coats that protect the timber and define how the deck looks on handover day.
This guide covers each decision in the quoting process with real 2026 Australian benchmarks so you can quote with confidence on every build.
Step 1: Calculate your true cost per hour
Before setting rates, work out what an hour of your time actually costs the business. This is your loaded hourly cost, covering everything required to have your crew on site with tools ready.
| Cost component | Typical annual range (sole operator or small crew) |
|---|---|
| Wages (including your own draw) | $70,000 - $100,000 |
| Superannuation (11.5%) | $8,050 - $11,500 |
| Vehicle and trailer (lease, fuel, rego, maintenance) | $14,000 - $24,000 |
| Insurance (public liability, vehicle, tools, construction) | $3,500 - $8,000 |
| Tools and equipment (saws, drill, driver, sander, laser level, clamps) | $3,000 - $7,000 |
| Licensing and training (builder's licence renewal, CPD) | $500 - $1,500 |
| Accounting, software, phone, admin | $2,500 - $5,500 |
| Workers comp (if employing) | $4,000 - $12,000 |
For a sole operator with one labourer, total annual costs typically land between $110,000 and $175,000. At 1,600-1,700 billable hours per year (allowing for rain days, travel, quoting time, and holidays), your loaded cost per hour sits between $65 and $109.
A two-person crew building a standard low-level deck can install 4-6 square metres of decking per day on treated pine, or 3-5 sqm per day on hardwood (which requires pre-drilling and is slower to cut). At a loaded daily crew cost of $1,200-1,600, that is $200-400 per square metre in labour alone before materials or margin. Your charge-out rate adds a healthy margin of 20-30% on top of costs.
Hardwood work wears through saw blades and drill bits faster than softwood. Budget $1,500-3,000 per year more in consumables if hardwood decking is the majority of your work.
Step 2: Choose the right material for the job and budget
Material choice is the single biggest variable in a decking quote. The board cost alone can range from $50 per square metre for treated pine to $300+ for premium composite. The right choice depends on the customer's budget, the deck's exposure, and the look they want.
Decking board costs (supply only, per sqm)
| Material | Cost per sqm (boards only) | Lifespan | Maintenance |
|---|---|---|---|
| Treated pine (H3/H4) | $50 - $80 | 15 - 20 years | Oil or stain every 1-2 years |
| Merbau | $120 - $200 | 25 - 40 years | Oil every 6-12 months initially, then annually |
| Spotted gum | $130 - $220 | 25 - 40+ years | Oil annually |
| Blackbutt | $120 - $200 | 25 - 40 years | Oil annually |
| Ironbark | $150 - $250 | 40+ years | Oil annually (extremely hard, slow to weather) |
| Composite (mid-range) | $100 - $200 | 25 - 30 years | Wash annually, no oiling or staining |
| Composite (premium) | $180 - $350 | 25 - 30+ years | Wash annually, manufacturer warranty 25 years |
When to recommend each material
Treated pine suits budget projects, rental properties, and decks where cost matters more than appearance. It is the easiest timber to work with and the fastest to install.
Merbau is the most popular hardwood decking timber in Australia. Rich reddish-brown colour, stable, and forgiving to work with. It bleeds tannin when new, which stains concrete and paving beneath the deck. Warn customers about this and protect adjacent surfaces during the first few months.
Spotted gum is an Australian native hardwood with exceptional hardness (Janka 11.0 kN, more than double merbau at 4.7 kN). It resists scratching and denting better than any other common decking timber. It requires pre-drilling for every fastener and is harder to cut cleanly, so factor slower installation into your labour estimate.
Composite suits customers who want minimal maintenance. Higher upfront cost, but no oiling, staining, or sanding over the deck's life. The lifetime cost can be comparable to hardwood once you factor in annual oiling and periodic sanding. Composite is also consistent in colour and does not splinter, which matters for families with children.
Step 3: Price the subframe, fasteners, and finishing separately
The subframe is the structure beneath the boards: stumps or posts, bearers, and joists. It accounts for 25-40% of the total material cost and is where most underquoting happens because customers focus on the boards and builders sometimes absorb or understate the subframe to keep the headline price low.
Subframe costs (per sqm of deck area)
| Subframe material | Cost per sqm (supply) | Best use |
|---|---|---|
| Treated pine (H4 bearers and joists) | $30 - $60 | Budget decks, low-level decks, treated pine board decks |
| Hardwood (merbau or similar bearers and joists) | $50 - $90 | Hardwood board decks, elevated decks, long-span applications |
| Steel (galvanised or powder-coated) | $70 - $120 | Elevated decks, bushfire zones (BAL-29+), long spans, commercial |
Stumps and footings
| Footing type | Cost per stump (supply and install) | When to use |
|---|---|---|
| Concrete pier pad (pre-cast, ground level) | $15 - $40 | Low-level decks on stable ground |
| Concrete pier (poured in-ground, 300mm dia) | $40 - $80 | Standard residential elevated decks |
| Screw piles | $80 - $150 | Reactive soils, steep sites, fast installation |
| Steel post on concrete footing | $60 - $120 | Elevated decks, bushfire zones |
A typical 25 sqm deck needs 9-12 stumps depending on joist span and bearer layout. At $40-80 each for standard poured piers, that is $360-960 in footings alone.
Fasteners
| Fastener type | Cost per sqm | Notes |
|---|---|---|
| Stainless steel screws (face-fixed) | $8 - $14 | Standard for hardwood. Use 305 or 316 grade for coastal. |
| Concealed clip system | $14 - $25 | Cleaner finish, slower to install, suits grooved-edge boards. |
| Composite-specific screws or clips | $10 - $18 | Supplied by composite manufacturer. Use the recommended system. |
| Joist protection tape | $3 - $6 | Applied to joist tops before boarding. Extends subframe life. |
Finishing (timber decks only)
| Finish type | Cost per sqm (supply and apply) | Notes |
|---|---|---|
| Decking oil (2 coats) | $8 - $15 | Standard finish for merbau, spotted gum, blackbutt. |
| Stain (2 coats) | $10 - $18 | Used on treated pine to add colour and UV protection. |
| No finish (weather to grey) | $0 | Some customers prefer the natural grey. Discuss lifespan impact. |
Always quote the first coat of oil or stain as part of the build. Handing over an unfinished timber deck invites complaints about the look and leaves the timber exposed to UV and moisture from day one. If the customer declines finishing, note it in the quote and your terms.
Step 4: Benchmark against current market rates
These are 2026 fully installed rates (all materials, subframe, fasteners, labour, and first coat of finish) for residential decking in Australian metro areas. Rates exclude balustrades, stairs, council fees, and demolition of existing structures.
Installed rates by material
| Material | Per sqm range (installed) | Typical project (25 sqm) |
|---|---|---|
| Treated pine (H3 boards, H4 subframe) | $200 - $350 | $5,000 - $8,750 |
| Merbau (hardwood subframe) | $300 - $500 | $7,500 - $12,500 |
| Spotted gum (hardwood subframe) | $320 - $500 | $8,000 - $12,500 |
| Blackbutt (hardwood subframe) | $300 - $480 | $7,500 - $12,000 |
| Composite mid-range (steel or pine subframe) | $350 - $500 | $8,750 - $12,500 |
| Composite premium (steel subframe) | $450 - $600 | $11,250 - $15,000 |
Regional variation
| City | Treated pine per sqm | Merbau per sqm |
|---|---|---|
| Sydney | $250 - $380 | $350 - $550 |
| Melbourne | $230 - $360 | $320 - $520 |
| Brisbane | $200 - $340 | $300 - $480 |
| Perth | $220 - $350 | $310 - $500 |
| Adelaide | $200 - $330 | $290 - $470 |
| Canberra | $230 - $360 | $320 - $510 |
| Hobart | $210 - $340 | $300 - $480 |
| Darwin | $240 - $370 | $330 - $520 |
| Regional areas | $190 - $320 | $280 - $460 |
Sydney prices run 10-15% above Brisbane due to higher labour rates, timber transport costs, and council fee structures. Darwin carries a premium from remoteness and the requirement for termite-resistant materials in all structural timber. Regional areas are generally lower on labour but can be higher on material delivery if the nearest timber yard is a long drive from site.
Step 5: Price the extras that customers underestimate
On most deck builds, the extras account for 20-40% of the total project cost. Quoting them as separate line items protects your margin and sets clear expectations.
Stairs
| Stair type | Cost (supply and install) |
|---|---|
| Simple timber stairs (3-5 risers, open stringers) | $800 - $1,800 |
| Wider or enclosed stairs (3-5 risers) | $1,200 - $2,500 |
| Wrap-around or L-shaped stairs | $2,000 - $4,500 |
| Each additional riser above 5 | $150 - $350 |
Balustrades
| Balustrade type | Cost per lineal metre (installed) |
|---|---|
| Timber (hardwood posts and rails) | $150 - $350 |
| Stainless steel wire | $350 - $600 |
| Glass (semi-frameless) | $400 - $700 |
| Glass (frameless) | $600 - $1,000 |
| Aluminium (powder-coated) | $200 - $400 |
The Building Code of Australia requires a balustrade on any deck more than 1 metre above finished ground level. The balustrade must be at least 1 metre high with no climbable elements and openings no wider than 125mm. For decks beside pools, the balustrade must also comply with pool fencing requirements. Always confirm the requirement before quoting and include the cost as a visible line item.
Demolition and site preparation
| Item | Typical cost |
|---|---|
| Remove existing timber deck (per sqm) | $30 - $60 |
| Remove existing concrete patio (per sqm) | $40 - $80 |
| Skip bin (3-4 cubic metres) | $300 - $550 |
| Site levelling and clearing | $200 - $800 |
| Weed mat and gravel beneath deck | $8 - $15/sqm |
| Termite treatment (chemical barrier) | $15 - $30/sqm |
Council permits and drawings
| Item | Typical cost |
|---|---|
| Development application / building permit | $200 - $1,500 |
| Structural engineering drawings | $500 - $2,000 |
| Building certification (private certifier) | $500 - $1,500 |
Council approval is typically required when the deck is more than 600mm to 1 metre above natural ground level, depending on the state. In Queensland the threshold is 1 metre. In Victoria it is 1 metre or 20 sqm. In NSW, decks under 1 metre and under 25 sqm may qualify as exempt development. Heritage overlays, bushfire zones, and flood zones can override these exemptions. Always check before quoting and include permit costs as a line item.
Step 6: Understand your licensing obligations
Deck building is classified as building work in every Australian state. Licensing requirements vary by state and by the value of the work. Include the cost of maintaining your licence in your overhead calculation.
| State | Regulator | Licence threshold | Typical licence class |
|---|---|---|---|
| NSW | NSW Fair Trading | Residential work over $1,000 inc GST | Contractor licence (General Building or Carpentry) |
| VIC | VBA | Domestic work over $5,000 inc GST | DB-L (Domestic Builder Limited) or DB-U (Unlimited) |
| QLD | QBCC | Residential work over $3,300 inc GST | Trade contractor (Carpentry) or Builder |
| WA | DEMIRS | Contract work over $20,000 | Registered Building Contractor |
| SA | Consumer and Business Services | Varies by work type | Building Work Contractors licence |
| TAS | CBOS | Work over $20,000 or requiring a building permit | Builder (limited or open) |
| ACT | Access Canberra | All construction work requires a licence | Builder or Specialist Building licence |
| NT | NT Building Advisory Services | Varies by building class | Registered Builder |
In NSW, the threshold is $1,000, which means virtually every decking job requires a licensed contractor. In Victoria, a DB-L licence holder can build a deck as long as it does not require the skills of a DB-U (unlimited) builder. Check your state authority for the exact requirements and ensure your licence class covers the scope of work you are quoting.
Step 7: Build a detailed line-item breakdown
Assembling the quote as a clear, itemised document builds trust and reduces disputes. Every element gets its own line and price, so variations are straightforward to handle.
Worked example: 30 sqm merbau deck with stairs and timber balustrade, Melbourne
Scope: remove existing 30 sqm treated pine deck (rotted bearers), install new concrete pier footings, hardwood bearer and joist subframe, 140x19mm merbau boards face-fixed with stainless steel screws, 4-riser timber staircase, 8 lineal metres of hardwood balustrade with stainless wire infill, two coats of decking oil, weed mat and gravel beneath. Deck height 600mm above ground (just under council permit threshold). Flat site, good access.
| Line item | Calculation | Amount (ex GST) |
|---|---|---|
| Remove existing deck and dispose | 30 sqm x $45/sqm | $1,350.00 |
| Skip bin (3 cubic metres) | 1 bin | $380.00 |
| Weed mat and gravel beneath deck | 30 sqm x $12/sqm | $360.00 |
| Concrete pier footings (10 piers, 300mm dia, poured in-ground) | 10 x $60 | $600.00 |
| Hardwood bearers and joists (supply and install) | 30 sqm x $70/sqm | $2,100.00 |
| Joist protection tape | 30 sqm x $4/sqm | $120.00 |
| Merbau decking boards 140x19mm (supply, 8% waste) | 32.4 sqm x $160/sqm | $5,184.00 |
| Stainless steel screws (face-fixed, 305 grade) | 30 sqm x $10/sqm | $300.00 |
| Timber staircase (4 risers, open stringers, merbau treads) | 1 set | $1,400.00 |
| Hardwood balustrade with stainless wire infill (8 lm) | 8 lm x $450/lm | $3,600.00 |
| Decking oil (2 coats, boards and stairs) | 35 sqm x $12/sqm | $420.00 |
| Labour: demolition, subframe, boarding, stairs, balustrade, finishing (2 crew x 6 days) | 12 person-days | $5,400.00 |
| Site clean-up | Allowance | $250.00 |
| Subtotal (ex GST) | $21,464.00 | |
| GST (10%) | $2,146.40 | |
| Total (inc GST) | $23,610.40 |
That works out to approximately $787 per square metre of deck area including GST, though this includes demolition of the old deck, stairs, and 8 metres of wire balustrade. The deck boards and subframe alone (without extras) sit at approximately $390 per sqm installed, which is within the expected $300-500 range for merbau in Melbourne.
Key points in this quote: the 8% waste factor on boards accounts for cutting, end-matching, and rejected pieces (hardwood has more variation than softwood); the balustrade is the single largest extra at $3,600 and is clearly visible as a separate line; the finishing is quoted as part of the build rather than left for the customer to arrange; and each line item can be adjusted independently if the customer changes scope or material.
Seven common quoting mistakes deck builders make
- Underpricing the subframe. Customers focus on the decking boards. Builders sometimes thin the subframe quote to keep the headline number competitive. The subframe is 25-40% of the material cost and is the structural skeleton of the deck. Underquote it and the margin disappears into bearers and joists.
- Forgetting the finishing. Two coats of decking oil on a 30 sqm deck costs $360-540 in product and labour. If you absorb it, that comes straight off your profit. If you leave the deck unfinished, the customer sees raw timber that starts greying within weeks and blames your workmanship. Quote it, apply it, hand over a finished product.
- Not accounting for waste on hardwood. Hardwood boards have more natural variation in colour, grain, and straightness than treated pine. Budget 8-10% waste for merbau and 10-12% for spotted gum (which can have significant bow). Ordering tight on hardwood means a second delivery mid-build, with a new batch that may not colour-match the first.
- Ignoring the demolition. Removing an existing deck is labour-intensive. A 30 sqm timber deck demolition with disposal costs $1,200-2,200. If the customer says "just build over it," inspect the existing structure first. Building on a rotted subframe is a liability.
- Skipping the council check. If the deck requires council approval and you build without it, the customer faces enforcement action and you face a defect claim. Check the height, area, and any overlay zones before quoting. Include permit costs as a line item when required. The 15 minutes spent checking saves a project-killing dispute later.
- Quoting without a site visit. A deck that sounds like "30 sqm, ground level, easy" on the phone can turn out to be on a slope, over tree roots, with limited access for material delivery, and an existing concrete patio to demolish. Measure the site, check the fall, assess access, and look at what is underneath. Every site condition has a cost.
- Presenting a single lump sum. A quote that says "$23,000 for a merbau deck" gives the customer one number to compare and no visibility into the components. An itemised quote lets them see the cost of each element, makes material upgrades or downgrades easy to price, and reduces the chance of a dispute over what was and was not included.
Frequently asked questions
How much does decking cost per square metre in Australia in 2026?
Treated pine decking costs $200-350 per square metre fully installed in 2026. Hardwood (merbau, spotted gum, blackbutt) runs $300-500 per sqm. Composite decking runs $350-600 per sqm. These are installed rates including subframe, fasteners, and labour, but excluding balustrades, stairs, council fees, and demolition of existing structures. Costs vary by location (Sydney runs 10-15% above Brisbane), deck height, site access, and material choice.
What is the cheapest decking material in Australia?
Treated pine (H3 or H4 rated) is the cheapest decking material at $50-80 per square metre for boards only, or $200-350 per sqm fully installed. It suits budget projects and decks where cost matters more than appearance. It requires oiling or staining every 1-2 years and lasts 15-20 years with maintenance. Hardwoods cost more upfront but last 25-40 years with less frequent maintenance.
How much do deck builders charge per hour in Australia?
Deck builders typically charge $60-100 per hour for labour, though most residential work is quoted per square metre or as a project price. Hourly rates suit small repair jobs, board replacements, and maintenance. For new builds, per-sqm or project pricing is standard because it reflects the full scope and is easier for customers to compare across quotes.
Do you need council approval to build a deck in Australia?
In most states, a deck less than 600mm to 1 metre above natural ground is exempt from council approval, subject to size limits. In Queensland, approval is required above 1 metre. In Victoria, above 1 metre or over 20 sqm. In NSW, decks under 1 metre high and under 25 sqm may qualify as exempt development. Heritage, bushfire, and flood overlays can override these exemptions. Always check with your local council before quoting.
Is merbau or spotted gum better for decking?
Both are excellent choices. Merbau (Durability Class 1-2, Janka 4.7 kN) is stable, easy to work, and has a warm reddish-brown colour. It bleeds tannin when new, staining adjacent surfaces. Spotted gum (Durability Class 1, Janka 11.0 kN) is harder, more scratch-resistant, and a native Australian species. It requires pre-drilling and is harder to cut. Both last 25-40 years. Merbau boards cost $120-200/sqm; spotted gum runs $130-220/sqm. Choose merbau for workability and warmth, spotted gum for hardness and provenance.
How much does a deck balustrade cost?
Timber balustrades cost $150-350 per lineal metre installed. Stainless steel wire runs $350-600/lm. Semi-frameless glass costs $400-700/lm. Frameless glass runs $600-1,000/lm. A 12-metre balustrade run adds $1,800-12,000 depending on material. Balustrades are required on any deck more than 1 metre above ground level under the Building Code of Australia.
How long does it take to build a deck?
A standard 20-30 sqm deck on low bearers takes 3-5 days for a two-person crew. An elevated deck with stairs and balustrades takes 5-10 days. Multi-level decks or those needing council approval can take 2-4 weeks including the approval wait. Factor build time into your schedule, as weather delays are common on outdoor carpentry work.
How long should it take to prepare a decking quote?
A straightforward single-level deck takes 30-60 minutes to quote after a site visit. A complex deck with multiple levels, stairs, balustrades, and council requirements takes 2-4 hours. FlowSpec cuts quoting time by letting you speak your line items on site and sending the priced quote to Xero automatically.