How to Quote Kitchen Renovation Jobs
A practical quoting guide for Australian builders and renovation contractors. Covers demolition, cabinetry, benchtops (including the engineered stone ban), plumbing, electrical, splashbacks, appliance allowances, common job benchmarks, council and licensing requirements by state, and how to present kitchen quotes that win work and protect your margin.
Why kitchen renovation quoting is the highest-stakes room in the house
Kitchens involve more trades, more material decisions, and more customer emotion than any other room. A bathroom has one benchtop, one splashback, and a wet area. A kitchen has cabinetry across three or four walls, a benchtop with cutouts and joins, plumbing for the sink and dishwasher, electrical for a dozen power points and the rangehood, a splashback that ties the room together, flooring that transitions into the living area, and appliances worth $3,000 to $15,000 that the customer has been researching for months.
The builders who profit from kitchen work quote every one of those layers as a separate line item. The ones who struggle lump everything into a round number, absorb the demolition and electrical costs to keep the headline figure competitive, and then discover they have no margin left when the plumber finds galvanised pipes behind the wall.
This guide covers each component with real 2026 Australian benchmarks so you can build profitable kitchen quotes on every job.
Step 1: Calculate your true cost per hour
Before pricing any kitchen job, work out what an hour of your time actually costs the business. This is your loaded hourly cost, covering everything required to have your crew on site with tools ready.
| Cost component | Typical annual range (sole operator or small crew) |
|---|---|
| Wages (including your own draw) | $70,000 - $110,000 |
| Superannuation (12%) | $8,400 - $13,200 |
| Vehicle (lease, fuel, rego, maintenance) | $12,000 - $22,000 |
| Insurance (public liability, construction, tools) | $4,000 - $10,000 |
| Tools and equipment | $3,000 - $6,000 |
| Licensing and training (builder's licence, CPD) | $500 - $2,000 |
| Accounting, software, phone, admin | $3,000 - $6,000 |
| Workers comp (if employing) | $4,000 - $12,000 |
| Home indemnity insurance (required in most states for renos over $12K-$20K) | $1,500 - $5,000 |
For a sole operator with one labourer, total annual costs typically land between $120,000 and $190,000. At 1,600-1,700 billable hours per year (allowing for quoting time, travel, admin, and holidays), your loaded cost per hour sits between $70 and $120.
Kitchen work is indoor, so rain delays are rare, but lead-time gaps between trades (waiting for the plumber, waiting for the electrician, waiting for cabinets) can leave your crew idle. Schedule trades tightly and price dead time into your overheads rather than absorbing it on each job.
Step 2: Assess and price the demolition
Every kitchen renovation starts with removing what is already there. The demolition scope sets the baseline cost that every other line item builds on.
Kitchen demolition costs (2026)
| Item | Cost range | Notes |
|---|---|---|
| Cabinet-only removal | $800 - $1,500 | Wall and base cabinets, benchtop, sink disconnection |
| Full kitchen strip-out | $1,500 - $4,000 | Cabinets, benchtop, splashback, flooring, wall patching |
| Full strip-out including flooring removal | $2,500 - $5,500 | Tiles, vinyl, or timber removed to subfloor |
| Skip bin (4-6 m3) | $300 - $600 | Standard kitchen demolition waste volume |
| Asbestos removal (if found) | $2,500 - $15,000 | Licensed removal required; see below |
The asbestos question
Any home built before 1990 (and some built up to the mid-1990s) may contain asbestos in splashback sheeting, vinyl flooring, wall and ceiling sheeting, or insulation behind the oven. You are legally required to have an asbestos assessment done before demolition work on pre-1990 properties. If asbestos is found, a licensed asbestos removalist must handle the material. Removal costs $50-150 per square metre for bonded (non-friable) asbestos, with a minimum charge of $1,500-2,500 for most contractors.
Include a provisional sum or exclusion clause in your quote for asbestos in older homes. A line reading "Excludes asbestos removal. If asbestos-containing materials are found during demolition, removal will be quoted separately by a licensed removalist" protects both you and the customer.
Step 3: Price the cabinetry
Cabinetry is the largest single cost in most kitchen renovations, typically 30-40% of the total project. The gap between flat-pack and fully custom joinery can be $15,000 to $30,000 on the same footprint. A standard kitchen runs 6-8 linear metres of cabinetry (base units, wall units, and a pantry or tall unit).
Cabinetry costs by type (per linear metre, installed)
| Cabinetry type | Cost per linear metre (installed) | Door finish | Typical total (7 lm kitchen) |
|---|---|---|---|
| Flat-pack (Kaboodle, Bunnings, IKEA) | $200 - $450 | Melamine wrap | $1,400 - $3,150 |
| Semi-custom (local manufacturer) | $450 - $900 | Melamine or vinyl wrap | $3,150 - $6,300 |
| Custom joinery (melamine or vinyl wrap) | $900 - $1,500 | Melamine, vinyl, or laminate | $6,300 - $10,500 |
| Custom joinery (two-pack polyurethane) | $1,500 - $2,200 | Two-pack spray finish | $10,500 - $15,400 |
| Custom joinery (Shaker profile or solid timber) | $1,800 - $2,800+ | Shaker, timber veneer, or solid timber | $12,600 - $19,600+ |
Flat-pack cabinets require 1-2 days of assembly labour (for a standard kitchen) on top of the unit cost. Factor this into your quote at your crew rate. Semi-custom and custom cabinets arrive assembled or part-assembled, reducing on-site labour but shifting cost into the cabinet supply price.
Cabinet hardware (hinges, drawer runners, pull-out bins, lazy susans, spice racks) adds $500-2,500 depending on quality. Soft-close hardware is now standard on anything above flat-pack. Specify the hardware brand and level in your quote.
Cabinet lead times
| Type | Lead time |
|---|---|
| Flat-pack (off the shelf) | Available immediately or 1-2 weeks delivery |
| Semi-custom | 3-5 weeks |
| Fully custom joinery | 4-10 weeks |
Lead times drive project scheduling. If cabinets take 8 weeks, demolition cannot start until week 6 at the earliest (assuming 2 weeks for demo, plumbing rough-in, electrical rough-in, plastering, and painting before cabinets arrive). Communicate lead times to the customer in your quote and build them into the project timeline.
Step 4: Quote the benchtop
Benchtops are the second largest material cost and the surface the customer will touch and see every day. The engineered stone ban has changed the benchtop conversation in Australia since mid-2024.
The engineered stone ban
On 1 July 2024, Australia banned the manufacture, supply, and installation of engineered stone products containing crystalline silica. On 1 January 2025, importation was also banned. This covers the brands that dominated the market for 15 years (Caesarstone, Smartstone, Essastone, and similar). The ban is a workplace health and safety measure to prevent silicosis in stonemasons and fabricators.
Low-silica engineered stone alternatives have entered the market from some manufacturers. These are compliant and available at similar price points. Natural stone (granite, marble, quartzite), porcelain slabs, laminate, timber, concrete, and stainless steel are all unaffected by the ban.
Benchtop costs by material (per sqm, supply and install)
| Material | Cost per sqm (installed) | Best for | Watch out for |
|---|---|---|---|
| Laminate (post-formed) | $120 - $330 | Budget renovations, rentals | Limited edge profiles, heat damage from hot pans |
| Low-silica engineered stone | $450 - $1,000 | Mid-range to premium, uniform look | Confirm product is compliant with the ban; request supplier certification |
| Granite | $700 - $1,500 | Premium, natural variation wanted | Sealing required, heavy (structural check for islands) |
| Marble | $900 - $2,000 | Luxury, statement kitchens | Etches from acids (lemon, vinegar), regular sealing |
| Porcelain slab | $500 - $1,200 | Modern, thin-profile look | Harder to fabricate; specialist installers needed |
| Timber (hardwood, oiled) | $500 - $1,600 | Warm, natural aesthetic | Requires regular oiling, can mark from water rings |
| Concrete (polished) | $600 - $1,200 | Industrial or rustic look | Must be sealed, can crack if substructure moves |
| Stainless steel | $800 - $1,500 | Commercial-style kitchens | Scratches easily, fingerprints |
A typical kitchen benchtop area is 2.5-5 square metres (L-shape or U-shape with island). Cutouts for sinks and cooktops add $100-300 each. Edge profiles (waterfall ends, bullnose, mitred) add $50-150 per lineal metre on stone benchtops. Specify the exact material, thickness, edge profile, and number of cutouts in your quote.
Step 5: Price the plumbing
Kitchen plumbing covers the sink, tap, dishwasher connection, and (if applicable) gas line for the cooktop. Whether services stay in the same location or move to a new position makes a large difference to cost.
Kitchen plumbing costs (2026)
| Item | Cost range | Notes |
|---|---|---|
| Sink replacement (same location) | $250 - $500 | Labour only; customer supplies sink |
| Tap installation | $150 - $350 | Labour only; mixer tap standard |
| Dishwasher connection | $150 - $300 | Hot, cold, and waste connections |
| Complete plumbing (same location) | $1,500 - $2,500 | Rough-in and fit-off, no relocation |
| Complete plumbing (relocated services) | $2,500 - $4,000 | Pipe extensions for new sink or dishwasher position |
| Gas line for cooktop | $400 - $1,200 | From existing gas supply point; new run from meter adds more |
| Plumbed fridge connection | $200 - $500 | Water line for ice maker or filtered water |
Always subcontract plumbing to a licensed plumber and include their quote as a line item. Do not absorb plumbing into a round "trades" figure. If the customer changes the sink position during the build, the plumbing cost changes significantly. A clear line item makes variations easy to price and justify.
Step 6: Price the electrical
Kitchen electrical is often underquoted. A modern kitchen requires more circuits and power points than most other rooms in the house, and the existing wiring in an older home may not be compliant.
Kitchen electrical costs (2026)
| Item | Cost range | Notes |
|---|---|---|
| Power point installation (each) | $140 - $200 | Supply and install, standard double GPO |
| Oven circuit (dedicated 20A or 32A) | $300 - $600 | Required for most wall ovens and freestanding cookers |
| Cooktop circuit (dedicated 32A) | $350 - $700 | Induction cooktops draw 6-8 kW; some need 40A |
| Rangehood wiring and switch | $200 - $450 | Includes ducting penetration if external |
| Under-cabinet LED lighting | $400 - $1,200 | Strip LED with driver; length dependent |
| Pendant lighting (per pendant) | $150 - $350 | Supply, wire, and install; excluding fitting cost |
| Downlight installation (per light) | $70 - $130 | LED downlight supply and install |
| Switchboard upgrade | $1,200 - $3,500 | If existing board lacks capacity for new circuits |
| Complete kitchen electrical (basic upgrade) | $1,500 - $3,500 | 6-10 GPOs, lighting, oven circuit, existing board OK |
| Complete kitchen electrical (full rewire) | $3,500 - $8,000 | New circuits, switchboard upgrade, induction, lighting design |
Induction cooktops are increasingly popular in Australian kitchen renovations. A high-powered induction cooktop (7.2-8.4 kW) needs a dedicated 32A or 40A circuit. If the existing switchboard is full, a switchboard upgrade is required before the electrician can add new circuits. Include a provisional sum for switchboard work in your quote for older homes.
Step 7: Price the splashback
The splashback covers the wall between the benchtop and wall cabinets, plus the area behind the cooktop. A typical kitchen splashback area is 2-5 square metres.
Splashback costs by material (per sqm, installed)
| Material | Cost per sqm (installed) | Notes |
|---|---|---|
| Ceramic subway tiles | $80 - $180 | Most popular option; classic look, easy to source |
| Porcelain tiles | $100 - $250 | Harder and more water-resistant than ceramic |
| Mosaic tiles | $150 - $350 | Feature areas; complex grouting increases labour |
| Large-format porcelain | $200 - $400 | Fewer grout lines, modern look; needs experienced tiler |
| Toughened glass (back-painted) | $250 - $750 | Seamless look, any colour; cutouts for power points add cost |
| Mirror glass | $300 - $700 | Makes small kitchens feel larger; shows every mark |
| Pressed metal | $100 - $250 | Heritage or industrial look; limited colour range |
| Stone slab (matching benchtop) | $500 - $1,500 | Seamless bench-to-splash look; heavy, needs strong fixing |
Glass splashbacks require a site measure after the cabinets and benchtop are installed, adding a second visit for the glazier. Factor this into your project schedule. Tile splashbacks can be installed before or after cabinets depending on the design, but most kitchen tilers prefer to tile after cabinets are in place for a cleaner finish line.
Step 8: Price the flooring
Kitchen flooring needs to handle water, dropped items, and heavy foot traffic. A typical kitchen floor area is 8-15 square metres. Many renovations include the adjoining dining or living area for a seamless transition.
Kitchen flooring costs (per sqm, installed)
| Material | Cost per sqm (installed) | Notes |
|---|---|---|
| Vinyl plank (click-lock) | $50 - $120 | Waterproof, soft underfoot, fast install |
| Porcelain floor tiles | $80 - $200 | Durable, waterproof; cold underfoot without heating |
| Ceramic floor tiles | $60 - $150 | Budget-friendly; less durable than porcelain |
| Engineered timber | $90 - $200 | Real timber look; not ideal near dishwashers without protection |
| Polished concrete | $50 - $100 | Usually existing slab; grind, seal, and polish |
| Natural stone tiles | $150 - $400 | Premium look; requires sealing |
Old flooring removal adds to the demolition cost. Tiles on a concrete slab cost $25-50 per sqm to remove. Vinyl or timber over timber subfloor is faster at $10-25 per sqm. If the existing floor is level and sound, some materials (vinyl plank, engineered timber) can be installed directly over the top, saving removal costs.
Step 9: Handle appliances clearly
Appliances are the most common source of kitchen quote disputes. Be explicit about who is supplying them and what your installation allowance covers.
Two approaches
Customer-supplied appliances: The customer buys their own oven, cooktop, rangehood, and dishwasher. You include an installation allowance per appliance ($100-300 each). This keeps your quote lower and avoids warranty responsibility for the appliances. State clearly in your quote: "Appliances to be supplied by the client. Installation allowance of $X per appliance is included. Appliances must be on site before the scheduled installation date."
Builder-supplied appliances: You source the appliances, mark them up 10-20%, and include them as line items. This gives you control over the schedule (no waiting for the customer's delivery) and adds margin. Specify the exact make, model, and price for each appliance. If the customer changes their mind after you have ordered, your quote should include a restocking or cancellation clause.
Typical appliance installation costs (labour only)
| Appliance | Installation cost | Notes |
|---|---|---|
| Wall oven | $150 - $300 | Electrician required for hardwiring |
| Cooktop (electric/induction) | $150 - $250 | Electrician required; benchtop cutout by fabricator |
| Cooktop (gas) | $200 - $400 | Licensed gasfitter required |
| Rangehood | $150 - $350 | Ducted adds penetration and ductwork cost |
| Dishwasher | $100 - $200 | Plumber for water and waste connections |
| Microwave (built-in) | $100 - $200 | Trim kit and power point required |
Step 10: Include painting, plastering, and finishing
After demolition, plumbing and electrical rough-in, and before cabinet installation, the walls and ceiling need patching and painting. This step is often underquoted or forgotten entirely.
| Item | Cost range | Notes |
|---|---|---|
| Wall patching and plastering (kitchen area) | $500 - $1,500 | After old cabinet removal; depends on wall condition |
| Ceiling repair (if water damage or removal of bulkhead) | $300 - $1,000 | Plasterboard and skim coat |
| Painting (walls and ceiling, kitchen area) | $800 - $2,000 | Prep, 2-3 coats; Dulux Wash&Wear or similar kitchen-grade paint |
| Cornice and trim replacement | $200 - $600 | If damaged during demolition or replacing bulkhead |
Common kitchen renovation benchmarks (2026)
These benchmarks cover complete renovations including demolition, all trades, and clean-up. They exclude appliances (customer-supplied) and assume services remain in the same location.
Small kitchen (5-8 sqm, galley or single-wall, apartment or unit)
| Component | Budget | Mid-range | Premium |
|---|---|---|---|
| Demolition and waste | $1,200 | $1,800 | $2,500 |
| Cabinetry (4-5 lm) | $1,500 | $4,000 | $10,000 |
| Benchtop (2-3 sqm) | $400 | $2,000 | $4,500 |
| Plumbing | $1,200 | $1,800 | $2,500 |
| Electrical | $1,200 | $2,500 | $4,000 |
| Splashback (2-3 sqm) | $300 | $600 | $2,000 |
| Flooring (5-8 sqm) | $400 | $1,000 | $2,400 |
| Painting and plastering | $800 | $1,200 | $1,800 |
| Clean-up | $300 | $400 | $500 |
| Subtotal (ex GST, ex margin) | $7,300 | $15,300 | $30,200 |
| With 35% margin + GST | $12,340 | $25,890 | $51,070 |
Standard kitchen (10-15 sqm, L-shape or U-shape, typical house)
| Component | Budget | Mid-range | Premium |
|---|---|---|---|
| Demolition and waste | $1,800 | $2,500 | $3,500 |
| Cabinetry (6-8 lm) | $2,500 | $6,500 | $18,000 |
| Benchtop (3-5 sqm) | $700 | $3,500 | $8,000 |
| Plumbing | $1,500 | $2,200 | $3,500 |
| Electrical | $1,500 | $3,000 | $6,000 |
| Splashback (3-5 sqm) | $400 | $900 | $3,000 |
| Flooring (10-15 sqm) | $700 | $1,800 | $4,500 |
| Painting and plastering | $1,000 | $1,500 | $2,500 |
| Clean-up | $400 | $500 | $600 |
| Subtotal (ex GST, ex margin) | $10,500 | $22,400 | $49,600 |
| With 35% margin + GST | $17,770 | $37,880 | $83,910 |
Large kitchen (15-25 sqm, island, open-plan, large house)
| Component | Mid-range | Premium |
|---|---|---|
| Demolition and waste | $3,000 | $5,000 |
| Cabinetry (10-14 lm incl. island) | $10,000 | $35,000 |
| Benchtop (5-8 sqm incl. island) | $5,000 | $14,000 |
| Plumbing (dual sink or prep sink on island) | $3,000 | $5,000 |
| Electrical | $4,000 | $8,000 |
| Splashback (5-8 sqm) | $1,500 | $5,000 |
| Flooring (15-25 sqm) | $2,500 | $7,500 |
| Painting and plastering | $2,000 | $3,500 |
| Clean-up | $600 | $800 |
| Subtotal (ex GST, ex margin) | $31,600 | $83,800 |
| With 35% margin + GST | $53,440 | $141,730 |
Council approvals and compliance
Most like-for-like kitchen replacements (same layout, same services, no structural changes) do not require council approval. However, several common kitchen renovation scenarios do trigger approval requirements.
When council approval is typically required
- Removing or modifying a load-bearing wall (opening up to a dining area) requires a structural engineer's certificate and council approval in all states.
- Changing the building footprint (extending the kitchen into a courtyard, closing in a verandah) is regulated building work in every state.
- Relocating plumbing to a position outside the existing wet area may require hydraulic design certification.
- Heritage overlays can restrict even cosmetic changes in listed homes or heritage precincts.
Compliance costs
| Item | Cost range |
|---|---|
| Structural engineer's report (wall removal) | $500 - $2,000 |
| Council development application (minor works) | $200 - $1,500 |
| Private certifier (complying development certificate) | $1,000 - $3,000 |
| Building surveyor final inspection | $300 - $800 |
| Asbestos survey (pre-demolition, pre-1990 homes) | $300 - $800 |
Include council fees in your quote as a separate line item. If the scope of work might trigger an approval requirement, note it as a provisional item with an estimated cost rather than leaving it out entirely.
Licensing requirements by state
Builder licensing in Australia is managed by each state and territory separately. The thresholds, licence classes, and insurance requirements differ.
| State/Territory | Licence required above | Regulator | Key notes |
|---|---|---|---|
| NSW | $5,000 (incl. GST) | NSW Fair Trading | Specific Kitchen, Bathroom & Laundry Renovation licence class available |
| VIC | All structural work | VBA | Registered Building Practitioner required; separate KBL licence class |
| QLD | $3,300 (incl. labour + materials) | QBCC | Lowest threshold in Australia |
| WA | $20,000 | Building Commission WA | Highest mainland threshold; HIA not required under $20K |
| SA | $5,000 (prescribed work) | Consumer & Business Services SA | Building work contractor licence + $10K net assets + PL insurance |
| TAS | All building work | CBOS Tasmania | Registered building practitioner required regardless of value |
| ACT | $5,000 | Access Canberra | Cabinet makers exempt from trade licence; builder licence needed for overall project |
| NT | $12,000 | NT Building Advisory Services | Registered building practitioner for work above threshold |
Regardless of the builder licence threshold, plumbing work always requires a licensed plumber, electrical work always requires a licensed electrician, and gas work always requires a licensed gasfitter. These are separate licences from the builder's licence.
Home indemnity insurance (also called home warranty insurance) is required in most states for residential renovation work above certain thresholds (typically $12,000-$20,000). Check your state's requirements and factor the premium into your overheads.
Regional price variation across Australia
Kitchen renovation costs vary by city due to differences in labour rates, trade availability, and property values.
| City | Relative cost (national average = 100) | Notes |
|---|---|---|
| Sydney | 110 - 115 | Most expensive market; high labour rates and strong demand |
| Melbourne | 105 - 110 | Second highest; competitive trade market |
| Brisbane | 100 - 105 | Close to national average; growing demand |
| Perth | 100 - 105 | Trade shortages can push prices higher on complex jobs |
| Canberra | 105 - 110 | Small market with strong purchasing power; fewer trades available |
| Adelaide | 90 - 95 | Below national average; competitive pricing |
| Hobart | 90 - 95 | Lower labour costs offset by limited trade availability |
| Darwin | 105 - 115 | Supply chain costs and climate factors add to pricing |
| Regional/rural | 95 - 120 | Wide range; travel costs and trade scarcity drive upper end |
Regional and rural areas have a wider cost range because travel time and limited trade availability can push costs 10-20% above metro rates, while lower overheads and land costs pull some components down. Always price for your local market rather than using national averages.
Worked example: mid-range L-shape kitchen renovation in Melbourne
A homeowner in Melbourne's inner east wants to renovate their 12 sqm L-shape kitchen. The home was built in 1985 (asbestos survey required). The layout stays the same. Cabinetry is semi-custom with vinyl-wrap doors. Benchtop is low-silica engineered stone. Subway tile splashback. Vinyl plank flooring. Customer supplies appliances.
| Line item | Qty / scope | Cost (ex GST) |
|---|---|---|
| Asbestos survey | Pre-demolition inspection | $500 |
| Demolition and strip-out | Full kitchen, waste removal | $2,200 |
| Skip bin hire | 4 m3 | $400 |
| Cabinetry (semi-custom, vinyl wrap, soft-close) | 7 lm base + wall + pantry | $5,600 |
| Cabinet hardware upgrade (pull-out bins, lazy susan) | Lump sum | $800 |
| Benchtop (low-silica engineered stone, 20mm, square edge) | 3.5 sqm | $2,800 |
| Benchtop cutouts (sink + cooktop) | 2 cutouts | $400 |
| Splashback (white subway tiles, 300x75mm) | 3.5 sqm | $490 |
| Plumbing (sink, tap, dishwasher, same location) | Rough-in + fit-off | $1,800 |
| Electrical (8 GPOs, oven circuit, cooktop circuit, rangehood, under-cabinet LEDs, 4 downlights) | Complete kitchen electrical | $3,200 |
| Flooring (vinyl plank over existing subfloor) | 12 sqm | $1,080 |
| Wall plastering and patching | After old cabinet removal | $900 |
| Painting (walls and ceiling, 2 coats kitchen-grade) | Kitchen area | $1,200 |
| Appliance installation (oven, cooktop, rangehood, dishwasher) | 4 appliances, customer-supplied | $800 |
| Final clean | Lump sum | $400 |
| Subtotal (direct costs) | $22,570 | |
| Builder's margin (35%) | $12,153 | |
| Subtotal before GST | $34,723 | |
| GST (10%) | $3,472 | |
| Total price (inc GST) | $38,195 | |
This falls within the national mid-range benchmark ($25,000-$45,000 inc GST) and the Melbourne regional adjustment (5-10% above national average). The 35% margin yields $12,153 gross profit on this job, from which the builder covers overhead costs before net profit.
If the asbestos survey finds asbestos in the splashback sheeting, add $1,500-3,000 for licensed removal. If the switchboard needs upgrading, add $1,500-3,000. Both are noted as exclusions in the quote with estimated costs for customer awareness.
7 common kitchen quoting mistakes
- Absorbing demolition costs. Demolition and waste removal cost $1,500-5,500 on a full kitchen strip-out. Rolling this into a round number hides a real cost that the customer should see and understand.
- Underquoting electrical. Kitchens need more circuits, more power points, and often a switchboard upgrade that older homes do not have capacity for. Budget $1,500-8,000 for electrical, not $500.
- Forgetting the engineered stone ban. Quoting a benchtop material that is banned wastes your time and the customer's. Specify compliant materials from the start.
- Leaving appliances ambiguous. "Appliances not included" is not enough. State whether your quote includes installation labour for customer-supplied appliances, and if so, how many and what type.
- Ignoring cabinet lead times. Custom cabinets take 4-10 weeks. If your project timeline does not account for this, you have dead time on site (costing you) or overlap problems with other trades.
- No provisional sum for concealed conditions. Old houses hide surprises: asbestos, non-compliant wiring, rotted framing, missing noggings. A provisional sum or exclusion clause protects your margin.
- Confusing markup with margin. A 30% markup gives you a 23% margin. If your target is a 35% gross margin, your markup needs to be 54%. Track actual margins by back-costing every completed kitchen against the original quote.
Frequently asked questions
How much does a kitchen renovation cost in Australia in 2026?
A cosmetic refresh (new doors, benchtop, splashback, paint) costs $8,000-20,000. A mid-range full renovation with semi-custom cabinetry and stone benchtops costs $25,000-45,000. A premium custom kitchen costs $45,000-100,000 or more. The national median for a complete kitchen renovation is around $35,000 in 2026. Costs vary significantly by city, kitchen size, and material selections.
What is the biggest cost in a kitchen renovation?
Cabinetry is the single largest component, typically 30-40% of the total. For a $35,000 mid-range renovation, expect $10,000-14,000 on cabinetry alone. Benchtops are second at 10-15%, followed by appliances at 10-15%, and plumbing plus electrical combined at 10-15%.
Can I still use engineered stone for kitchen benchtops?
Traditional engineered stone containing crystalline silica was banned from manufacture, supply, and installation in Australia from 1 July 2024, and from importation on 1 January 2025. Low-silica alternatives from some manufacturers remain compliant and available at similar price points ($450-1,000 per sqm installed). Natural stone, porcelain slabs, laminate, timber, and stainless steel are all unaffected.
Do I need a builder's licence for kitchen renovations?
It depends on your state. NSW requires a licence for work over $5,000 (GST inclusive). Queensland requires one for work over $3,300. Victoria requires registration for structural work at any value. WA has the highest mainland threshold at $20,000. Plumbing and electrical always require separately licensed tradespeople regardless of the overall project value.
How long does a kitchen renovation take?
A cosmetic refresh takes 1-2 weeks. A mid-range full renovation takes 4-8 weeks from demolition to final clean. A high-end custom kitchen takes 8-16 weeks, with 4-8 weeks of cabinet manufacture lead time. Schedule trades tightly and communicate lead times to the customer from the start.
Should I quote fixed price or cost-plus?
Fixed-price quoting is standard for kitchen renovations in Australia and is legally required in most states for domestic work above certain thresholds. The key to profitable fixed-price work is thorough scoping before you price. Include provisional sums or exclusion clauses for concealed conditions (asbestos, non-compliant wiring, rotted framing) to protect your margin on unknowns.
What margin should I target on kitchen renovations?
Target a gross profit margin of 30-40%. A 35% gross margin on a $40,000 kitchen yields $14,000 in gross profit, from which you cover your fixed overheads before net profit. If your actual margins consistently fall below 25%, tighten your scoping or pricing process. Back-cost every completed job against the original quote to track real margins.
How long should it take to prepare a kitchen renovation quote?
A straightforward like-for-like kitchen replacement takes 2-4 hours after a site visit. A complex renovation with layout changes, structural work, and custom joinery takes 4-8 hours. FlowSpec cuts quoting time by letting you speak your line items on site and sending the priced quote to Xero automatically.